Ready to launch: Bengaluru Yellow Line Metro Gets Railway Board Approval, Inspection Expected by End of May 2025

Bengaluru Yellow Line Metro Gets Railway Board Approval

Bengaluru Yellow Line Metro Gets Railway Board Approval

Bengaluru, May 2025 – The much-awaited Yellow Line of Namma Metro is moving one step closer to launch. The Bangalore Metro Rail Corporation Limited (BMRCL) has received approval from the Railway Board for its rolling stock — an important milestone before operations can begin.

✅ Current Status of the Yellow Line

The 19.15 km corridor between R.V. Road and Bommasandra is now structurally complete. A third train set is expected to be ready for service within a week. However, the project has faced multiple delays, mostly due to the late delivery of driverless train sets.

📝 CMRS Inspection Likely by May-End

BMRCL officials have confirmed that they are awaiting the inspection schedule from the Commissioner of Metro Rail Safety (CMRS), Southern Range. The inspection is a mandatory safety check before any metro line can begin operations.

“Most documentation is submitted. Signalling certification will follow shortly. We hope the CMRS inspection will take place by the end of May,”

– BMRCL Official

📌 What will CMRS inspect?

After the inspection, BMRCL will need about two weeks to make any required changes. This means partial services could begin by mid or end of June 2025.

📍 Importance of the Namma Metro Yellow Line

The Yellow Line will connect South Bengaluru, including the major tech hub Electronics City, with the rest of the city’s metro network. It is expected to:

📌 Key Points

🚧 Delays and Challenges Faced

Despite structural readiness, the project faced serious delays. In 2019, Chinese firm CRRC won a ₹1,578-crore contract to supply 216 driverless coaches. However, the company failed to set up a manufacturing unit in India, causing disruptions.

As a result:

Later, CRRC partnered with Titagarh Rail Systems from Kolkata to fulfill the contract. This helped resume deliveries, though delays continued.

🗓️ Project Timeline

🚆 Trial Runs and Train Availability

Once fully operational, the Yellow Line will significantly enhance the city’s metro network, especially for South Bengaluru residents.

📅 When Can We Expect Operations to Start?

Based on current progress and pending CMRS approval, partial service on the Yellow Line is expected to begin by mid or end of June 2025. Initially, trains will stop only at key stations with limited frequency.


🟡 Quick Summary

Stay tuned for more updates as Bengaluru gets ready to welcome the Yellow Line!